Haw. Code R. § 12-222.1-5

Current through August, 2024
Section 12-222.1-5 - Technical installation requirements
(a) General requirements. The following shall apply to all power boilers:
(1) Power boilers shall be installed pursuant to section 12-220-2.1 and this chapter;
(2) Owners and users shall adhere to the power boiler installation requirements as specified in NBIC Part 1, and this chapter;
(3) An application for installation permit shall be submitted to the department prior to commencement of work;
(4) Boilers installed without an installation permit may be subject to citation and penalties of up to $10,000 per day pursuant to section 12-220-22;
(5) Only contractors holding a valid Hawaii C-4 contractor license issued by the contractors license board of the department of commerce and consumer affairs shall install power boilers; and
(6) All power boilers shall be equipped with controls and safety devices based upon the Btu/hr burner input, as specified in the original code of construction, and in accordance with the following codes and standards:
(A) Boilers with energy input ratings of less than 12,500,000 Btu/hr shall meet the requirements of ASME CSD-1-2012;
(B) Boilers with energy input ratings of 12,500,000 Btu/hr and above shall meet the requirements of NFPA-85-2015;
(C) All atmospheric fluidized bed boilers, boilers with pulverized fuel systems, and boilers that are stoker fired shall meet the requirements of NFPA-85-2015; and
(D) No new miniature boiler shall be installed unless it has been constructed and inspected to ASME BPVC standards, bears the ASME certification mark with the 'S", "M", or "E" designator in accordance with the requirements of Part PMB of ASME BPVC Section I, and when required, has controls and safety devices installed that are in accordance with ASME CSD-1-2012.
(b) First acceptance inspection and certification requirements shall include the following:
(1) The owner, user, and contractor shall comply with section 12-220-2.1, and upon completion of the installation shall arrange for an acceptance inspection by the department;
(2) The installing contractor shall operationally test the boiler controls and safety devices prior to scheduling the first acceptance inspection with the department and record the results on form CG-500, ASME CSD-1 2012, and file a copy with the department;
(3) First inspections for power boilers shall include internal inspection, pressure test in accordance with the original code of construction, and operational testing of the controls and safety devices;
(4) The installing contractor shall test the boiler as directed and witnessed by an inspector employed by the department;
(5) An inspector employed by the department shall conduct the first data inspection, acceptance, and mark the state serial number on the power boiler pursuant to section 12-220-29.1; and
(6) The installer shall complete and certify the NBIC Boiler Installation Report I-1 (NB-365, see Exhibit 3), found at the end of this chapter, after the completion, inspection, and acceptance of the installation. The Boiler Installation Report I-1 (NB-365, see Exhibit 3) shall be submitted to the owner and the department.
(c) The following shall apply to power boiler clearances:
(1) Boiler installations shall allow for normal operation, maintenance, and inspections. There shall be at least thirty-six (36) inches of clearance on each side of a boiler to enable access for maintenance and inspection activities. Boilers operated in battery shall not be installed closer than forty-eight (48) inches from each other. The front or rear of any boiler shall not be located closer than thirty-six (36) inches from any wall or structure;
(2) Alternative clearances in accordance with the manufacturer's recommendations are subject to acceptance by the department;
(3) Boilers shall be installed to allow for removal and installation of tubes;
(4) Boilers with a top-opening manhole shall have at least eighty-four (84) inches of unobstructed clearance above the manhole to the ceiling of the equipment room; other manhole openings shall have at least five (5) feet; and
(5) Boilers with a bottom opening used for inspection or maintenance shall have at least twelve (12) inches of unobstructed clearance.
(d) The following shall apply to electric and miniature boiler clearances:
(1) Electric and miniature boilers shall be installed at an accessible location for inspection and maintenance;
(2) Electric and miniature boilers shall not be installed in ceilings unless provided with permanent ladders, floors, and height clearance for safe access;
(3) Control sides and door openings shall have three (3) feet clearance from any type of interference;
(4) All other sides shall have eighteen (18) inches of clearance; and
(5) Alternative clearances in accordance with the manufacturer's recommendations are subject to acceptance by the department.

Haw. Code R. § 12-222.1-5

[Eff and comp 12/21/2019] (Auth: HRS § 397-4) (Imp: HRS § 397-4)