Haw. Code R. § 12-220-9.1

Current through August, 2024
Section 12-220-9.1 - Design, construction, fabrication installation, repair, or alteration of boiler external and non-boiler external piping
(a) Application for authorization for installation of boiler external piping shall be submitted to the department prior to the commencement of work. An application shall be submitted in the form prescribed by the director and must be accompanied by the remittance of the fee for each boiler external piping subject to this part as per the schedule in Exhibit A, titled, "Installation, Repair or Alteration Permit Fees, and Licensure, Examination, and Registration Fees", dated September 1, 2019, which is made part of this chapter and located at the end of this chapter, and inspection fee for each pressure retaining item subject to this part as per the schedule in Exhibit B, titled, "Internal & External Inspection Fees", dated September 1, 2019, which is made a part of this chapter and located at the end of this chapter. A complete application shall include:
(1) Date of application, project name, and address;
(2) Manufacturer's and installer's name, address, and installer's type of license held along with the expiration date;
(3) Contact person and phone number for the owner, manufacturer, and installer;
(4) National Board number of the boiler where the piping is to be installed;
(5) Copy of the ASME manufacturer's data report and partial data reports;
(6) Floor plan layout with clearance dimensions; and
(7) Piping and instrumentation diagram.
(b) Application for authorization for design, fabrication, installation, repair, or alteration of non-boiler external piping shall be submitted by a holder of a valid ASME certificate of authorization with 'S", "A", or "PP" designator, a NB "R" authorization, or a NBEP Hawaii certification of authorization, to the department prior to the commencement of work. An application shall be submitted on a form provided by the department and must be accompanied by the remittance of the fee for each non-boiler external piping subject to this part as per the schedule in Exhibit A, titled, "Installation, Repair or Alteration Permit Fees, and Licensure, Examination, and Registration Fees", dated September 1, 2019, which is made part of this chapter and located at the end of this chapter, and inspection fee for each pressure retaining item subject to this part as per the schedule in Exhibit B, titled, "Internal & External Inspection Fees", dated September 1, 2019, which is made a part of this chapter and located at the end of this chapter. A complete application shall include:
(1) Date of application, project name, and address;
(2) Manufacturer's and installer's name, address, and installer's type of license held along with the expiration date;
(3) Contact person and phone number for the owner, manufacturer, and installer;
(4) National Board number of the boiler where the piping is to be installed;
(5) Copy of the ASME manufacturer's data report;
(6) Floor plan layout with clearance dimensions; and
(7) Piping and instrumentation diagram.
(c) Repairs and alterations of NBEP shall be in accordance with NBIC Part 3 and ASME B31.1 whenever applicable. Repair inspector involvement may be waived, and stamping is not mandatory.

Haw. Code R. § 12-220-9.1

[Am and comp 12/21/2019] (Auth: § 397-4) (Imp: § 397-4)