The authority to construct or permit to operate shall continue to be in effect until the covered source permit is issued or denied, provided the owner or operator constructs or operates in accordance with the authority to construct or permit to operate, section 11-60.1-9, and any applicable laws, regulations, or rules in effect at the time of issuance of the authority to construct or permit to operate. Noncompliance with any condition of the authority to construct or permit to operate is considered a violation of this chapter.
SICC | Type of Covered Source | Number of months from effective date of this chapter when submission is due |
14 | Mining and quarrying of nonmetallic minerals, except fuels | Four months |
32 | Manufacturing stone, clay, glass, and concrete products | Four months |
2951 | Asphalt paving mixtures and blocks | Four months |
2952 | Asphalt felts and coatings | Four months |
01 | Agricultural production | Six months |
07 | Agricultural services | Six months |
49 | Electric, gas, and sanitary services All others | Eight months Ten months |
The director, upon written request from the owner or operator of a covered source, may extend the application submittal deadline if the director determines that reasonable justification exists for the extension. The written request for an extension shall be submitted at least thirty days prior to the required submission date and shall include the following information:
If the director disapproves an extension for initial application submittal, the owner or operator shall meet the scheduled submission date. Under no circumstances shall the deadline for submitting an initial covered source application be extended beyond twelve months from the effective date of this chapter.
Haw. Code R. § 11-60.1-87