Haw. Code R. § 11-60.1-9

Current through September, 2024
Section 11-60.1-9 - Cancellation of a noncovered or covered source permit
(a) If construction authorized by a noncovered source permit is not commenced within twelve months after the noncovered source permit takes effect, is discontinued for a period of twelve months or more, or is not completed within a reasonable time, the noncovered source permit shall become invalid with respect to the authorized construction.
(b) If construction authorized by a covered source permit is not commenced within eighteen months after the covered source permit takes effect, is discontinued for a period of eighteen months or more, or is not completed within a reasonable time, the covered source permit shall become invalid with respect to the authorized construction.
(c) Subsections (a) and (b) shall not apply to phased construction projects. Instead, each phase shall commence construction within eighteen months for a covered source, or twelve months for a noncovered source, of the projected and approved commencement dates in the permit.
(d) The director may extend the specified periods upon a satisfactory showing that an extension is justified.

Haw. Code R. § 11-60.1-9

[Eff 11/26/93; comp 10/26/98; comp 9/15/01; comp 11/14/03; comp 1/13/12; comp JUN 30 2014] (Auth: HRS §§ 342B-3, 342B-12; 42 U.S.C. §§7407, 7416) (Imp: HRS §§ 342B-3, 342B-12; 42 U.S.C. §§7407, 7416)
Historical note: § 11-60.1-9 is based substantially upon § 11-60-52. [Eff 11/29/82; am, ren § 11-60-52 and comp 4/14/86; am and comp 6/29/92; R 11/26/93]