Section 11-55-21 - Schedule of compliance in issued NPDES permits
(a) With respect to any discharge which is not in compliance with applicable effluent standards and limitations, applicable water quality standards, or other legally applicable requirements listed in section 11-55-19, the permit shall require the permittee to take specific steps to achieve compliance with the following:
(1) In accordance with any legally applicable schedule of compliance contained in:
(A) Applicable effluent standards and limitations;
(B) If more stringent, effluent standards and limitations needed to meet water quality standards; or
(C) If more stringent, effluent standards and limitations needed to meet legally applicable requirements listed in section 11-55-19; or
(2) In the absence of any legally applicable schedule of compliance, in the shortest, reasonable period of time, which shall be consistent with the guidelines and requirements of the Act.
(b) When a schedule specifies compliance longer than one year after permit issuance, the schedule of compliance shall specify interim requirements and the dates for their achievement and in no event shall more than one year elapse between interim dates. If the time necessary for completion of the interim requirement (such as the construction of a treatment facility) exceeds one year and is not readily divided into stages for completion, the schedule shall specify interim dates for the submission of reports of progress towards completion of the interim requirements. For each NPDES permit schedule of compliance, interim dates, reporting dates, and the final date for compliance shall, to the extent practicable, fall on the last day of the month of March, June, September, and December.

Haw. Code R. § 11-55-21

[Eff 11/27/81; am and comp 10/29/92; Eff 09/23/96; am and comp 09/22/97; comp 01/06/01; am and comp 11/07/02; comp 08/01/05; comp 10/22/07; comp JUN 15 2009] (Auth: HRS §§ 342D-4, 342D-5, 342D-6; 33 U.S.C. §§1251, 1342, 1370 ) (Imp: HRS §§ 342D-2, 342D-4, 342D-5, 342D-6, 342D-50; 33 U.S.C. §§1251, 1342, 1370, 1251-138740 CFR Parts 122; 123; 124, Subparts A and D; 125; §§122.43, 122.47, 123.25(a))
Comp 10/21/12; Comp 12/6/13; Comp 11/15/14; Comp 7/13/2018
Comp 2/9/2019
Comp OCT 22 2021
Comp 1/15/2022