Haw. Code R. § 11-503-3

Current through November, 2024
Section 11-503-3 - Fee schedules for notifications, accreditation, certification, and registration
(a) The fee schedule for demolition and renovation notifications shall be as follows:

Quantity of RACM to be DisturbedFee
Demolition Only-No Asbestos $ 50
Greater than or equal to 260 linear, 160 square, or 35 cubic feet, but less than 500 linear, square, or cubic feet $ 100
Greater than or equal to 500 linear, square or cubic feet, but less than 1000 linear, square, or cubic feet $ 225
Greater than or equal to 1000 linear, square or cubic feet, but less than 2500 linear, square, or cubic feet $ 300
Greater than or equal to 2500 linear, square, or cubic feet, but less than 5000 linear, square, or cubic feet $ 375
Greater than or equal to 5000 linear, square $ 450
or cubic feet, but less than 10,000 linear, square, or cubic feet
Greater than 10,000 linear, square, or cubic feet $ 525
Revision to or cancellation of Notifications $ 10

(b) The annual fee for accreditation of training providers shall be $1000.
(c) The fee schedule for certification shall be as follows:

Initial Annual Renewal
Worker $ 60.00 $30.00
Contractor/Supervisor 100.00 50.00
Project Designer 300.00 150.00
Project Monitor 150.00 75.00
Inspector 200.00 100.00
Management Planner 50.00 25.00

Maximum annual fee for any individual: Initial $375.00

Renewal $175.00.

(d) The annual fee for registration shall be as follows:

Asbestos contractor $200.00
Laboratory $100.00.

Haw. Code R. § 11-503-3