Haw. Code R. § 11-265-112

Current through November, 2024
Section 11-265-112 - Closure plan; amendment of plan
(a) Written plan. By six months after the effective date of the rule that first subjects a facility to provisions of this section, the owner or operator of a hazardous waste management facility must have a written closure plan. Until final closure is completed and certified in accordance with section 11-265-115, a copy of the most current plan must be furnished to the director upon request, including request by mail. In addition, for facilities without approved plans, it must also be provided during site inspections, on the day of inspection, to any officer, employee or representative of the department who is duly designated by the director.
(b) Content of plan. The plan must identify steps necessary to perform partial and/or final closure of the facility at any point during its active life. The closure plan must include, at least:
(1) A description of how each hazardous waste management unit at the facility will be closed in accordance with section 11-265-111; and
(2) A description of how final closure of the facility will be conducted in accordance with section 11-265-111. The description must identify the maximum extent of the operation which will be unclosed during the active life of the facility; and
(3) An estimate of the maximum inventory of hazardous wastes ever on-site over the active life of the facility and a detailed description of the methods to be used during partial and final closure, including, but not limited to methods for removing, transporting, treating, storing or disposing of all hazardous waste, identification of and the type(s) of off-site hazardous waste management unit(s) to be used, if applicable; and
(4) A detailed description of the steps needed to remove or decontaminate all hazardous waste residues and contaminated containment system components, equipment, structures, and soils during partial and final closure including, but not limited to, procedures for cleaning equipment and removing contaminated soils, methods for sampling and testing surrounding soils, and criteria for determining the extent of decontamination necessary to satisfy the closure performance standard; and
(5) A detailed description of other activities necessary during the partial and final closure period to ensure that all partial closures and final closure satisfy the closure performance standards, including, but not limited to, ground-water monitoring, leachate collection, and run-on and run-off control; and
(6) A schedule for closure of each hazardous waste management unit and for final closure of the facility. The schedule must include, at a minimum, the total time required to close each hazardous waste management unit and the time required for intervening closure activities which will allow tracking of the progress of partial and final closure. (For example, in the case of a landfill unit, estimates of the time required to treat or dispose of all hazardous waste inventory and of the time required to place a final cover must be included.); and
(7) An estimate of the expected year of final closure for facilities that use trust funds to demonstrate financial assurance under section 11-265-143 or section 11-265-145 and whose remaining operating life is less than twenty years, and for facilities without approved closure plans.
(c) Amendment of plan. The owner or operator may amend the closure plan at any time prior to the notification of partial or final closure of the facility. An owner or operator with an approved closure plan must submit a written request to the director to authorize a change to the approved closure plan. The written request must include a copy of the amended closure plan for approval by the director.
(1) The owner or operator must amend the closure plan whenever:
(i) Changes in operating plans or facility design affect the closure plan, or
(ii) There is a change in the expected year of closure, if applicable, or
(iii) In conducting partial or final closure activities, unexpected events require a modification of the closure plan.
(2) The owner or operator must amend the closure plan at least sixty days prior to the proposed change in facility design or operation, or no later than sixty days after an unexpected event has occurred which has affected the closure plan. If an unexpected event occurs during the partial or final closure period, the owner or operator must amend the closure plan no later than thirty days after the unexpected event. These provisions also apply to owners or operators of surface impoundments and waste piles who intended to remove all hazardous wastes at closure, but are required to close as landfills in accordance with section 11-265-310.
(3) An owner or operator with an approved closure plan must submit the modified plan to the director at least sixty days prior to the proposed change in facility design or operation, or no more than sixty days after an unexpected event has occurred which has affected the closure plan. If an unexpected event has occurred during the partial or final closure period, the owner or operator must submit the modified plan no more than thirty days after the unexpected event. These provisions also apply to owners or operators of surface impoundments and waste piles who intended to remove all hazardous wastes at closure but are required to close as landfills in accordance with section 11-265-310. If the amendment to the plan is a Class 2 or 3 modification according to the criteria in section 11-270-42, the modification to the plan will be approved according to the procedures in paragraph (d)(4).
(4) The director may request modifications to the plan under the conditions described in paragraph (c)(1). An owner or operator with an approved closure plan must submit the modified plan within sixty days of the request from the director, or within thirty days if the unexpected event occurs during partial or final closure. If the amendment is considered a Class 2 or 3 modification according to the criteria in section 11-270-42, the modification to the plan will be approved in accordance with the procedures in paragraph (d)(4).
(d) Notification of partial closure and final closure.
(1) The owner or operator must submit the closure plan to the director at least one-hundred and eighty days prior to the date on which he expects to begin closure of the first surface impoundment, waste pile, land treatment, or landfill unit, or final closure if it involves such a unit, whichever is earlier. The owner or operator must submit the closure plan to the director at least forty-five days prior to the date on which he expects to begin partial or final closure of a boiler or industrial furnace. The owner or operator must submit the closure plan to the director at least forty-five days prior to the date on which he expects to begin final closure of a facility with only tanks, container storage, or incinerator units. Owners or operators with approved closure plans must notify the director in writing at least sixty days prior to the date on which he expects to begin closure of a surface impoundment, waste pile, landfill, or land treatment unit, or final closure of a facility involving such a unit. Owners or operators with approved closure plans must notify the director in writing at least forty-five days prior to the date on which he expects to begin partial or final closure of a boiler or industrial furnace. Owners or operators with approved closure plans must notify the director in writing at least forty-five days prior to the date on which he expects to begin final closure of a facility with only tanks, container storage, or incinerator units.
(2) The date when he "expects to begin closure'' must be either:
(i) Within thirty days after the date on which any hazardous waste management unit receives the known final volume of hazardous wastes, or, if there is a reasonable possibility that the hazardous waste management unit will receive additional hazardous wastes, no later than one year after the date on which the unit received the most recent volume of hazardous wastes. If the owner or operator of a hazardous waste management unit can demonstrate to the director that the hazardous waste management unit or facility has the capacity to receive additional hazardous wastes and he has taken, and will continue to take, all steps to prevent threats to human health and the environment, including compliance with all interim status requirements, the director may approve an extension to this one-year limit; or
(ii) For units meeting the requirements of subsection 11-265-113(d), no later than thirty days after the date on which the hazardous waste management unit receives the known final volume of non-hazardous wastes, or if there is a reasonable possibility that the hazardous waste management unit will receive additional non-hazardous wastes, no later than one year after the date on which the unit received the most recent volume of non-hazardous wastes. If the owner or operator can demonstrate to the director that the hazardous waste management unit has the capacity to receive additional non-hazardous wastes and he has taken, and will continue to take, all steps to prevent threats to human health and the environment, including compliance with all applicable interim status requirements, the director may approve an extension to this one-year limit.
(3) The owner or operator must submit his closure plan to the director no later than fifteen days after:
(i) Termination of interim status except when a permit is issued simultaneously with termination of interim status; or
(ii) Issuance of a judicial decree or final order under HRS section 342J-7 to cease receiving hazardous wastes or close.
(4) The director will provide the owner or operator and the public, through a newspaper notice, the opportunity to submit written comments on the plan and request modifications to the plan no later than thirty days from the date of the notice. The director will also, in response to a request or at the director's own discretion, hold a public hearing whenever such a hearing might clarify one or more issues concerning a closure plan. The director will give public notice of the hearing at least thirty days before it occurs. (Public notice of the hearing may be given at the same time as notice of the opportunity for the public to submit written comments, and the two notices may be combined.) The director will approve, modify, or disapprove the plan within ninety days of its receipt. If the director does not approve the plan he shall provide the owner or operator with a detailed written statement of reasons for the refusal and the owner or operator must modify the plan or submit a new plan for approval within thirty days after receiving such written statement. The director will approve or modify this plan in writing within sixty days. If the director modifies the plan, this modified plan becomes the approved closure plan. The director must assure that the approved plan is consistent with sections 11-265-111 through 11-265-115 and the applicable requirements of subchapter F, sections 11-265-197, 11-265-228, 11-265-258, 11-265-280, 11-265-310, 11-265-351, 11-265-381, 11-265-404, and 11-265-1102. A copy of the modified plan with a detailed statement of reasons for the modifications must be mailed to the owner or operator.
(e) Removal of wastes and decontamination or dismantling of equipment. Nothing in this section shall preclude the owner or operator from removing hazardous wastes and decontaminating or dismantling equipment in accordance with the approved partial or final closure plan at any time before or after notification of partial or final closure.

Haw. Code R. § 11-265-112

[Eff 6/18/94; comp] (Auth: HRS §§ 342J-4, 342J-31, 342J-34, 342J-35) (Imp: 40 C.F.R. §265.112 )