Haw. Code R. § §§ 11-262.260

Current through November, 2024
Section 11-262.260 - Purpose and implementation of contingency plan
(a) A large quantity generator must have a contingency plan for the facility. The contingency plan must be designed to minimize hazards to human health or the environment from fires, explosions, or any unplanned sudden or nonsudden release of hazardous waste or hazardous waste constituents to air, soil, or surface water.
(b) The provisions of the plan must be carried out immediately whenever there is a fire, explosion, or release of hazardous waste or hazardous waste constituents which could threaten human health or the environment.

Haw. Code R. §§ 11-262.260

[Eff 7/17/2017] (Auth: HRS §§ 342J-4, 342J-31, 342J-32, 342J-35) (Imp: HRS §§ 342J-4, 342J-31, 342J-32, 342J-35)
Am and Comp 9/30/2018
Comp 6/25/2020
Comp 6/7/2021
Am and comp 1/29/2024