Haw. Code R. § 11-23-08

Current through November, 2024
Section 11-23-08 - Construction conditions
(a) No injection well shall be constructed unless, prior to the start of any construction:
(1) Application is made for a UIC permit and all application procedures set forth in sections 11-23-12 through 11-23-15 are completed;
(2) It is shown that the proposed injection well will comply with this chapter; and
(3) The department, upon satisfaction of the reguirements set forth in paragraphs (1) and (2), approves the start of construction.
(b) Approval of the start of the construction of any injection well shall not be construed as approval for the Operation of that injection well. Further, the approval of the start of construction does not guarantee the approval to operate upon completion of the injection well. Permits shall be issued only in accordance with this chapter and it is the duty of the applicant to insure compliance with the law and this chapter.

Haw. Code R. § 11-23-08

[Eff. 7/6/84 ; am and comp NOV 121992 ] (Auth: HRS § 340E-2) (Imp: HRS § 340E-2)