Current through Rules and Regulations filed through October 29, 2024
Rule 672-5-.12 - Effect of Subcontracting on Contractor's Capacity(1) The prime Contractor may subcontract portions of the project to other prequalified Contractors or registered Subcontractors up to the amount provided for in the contract specifications. In figuring the total amount of Current Capacity available to a Contractor, it will be given credit for the work subcontracted after the Subcontractor has been approved in writing by the Department.(2) No Person shall both prequalify as a Contractor and register as a Subcontractor. Any subcontract work undertaken by a prequalified Contractor shall be counted against its Current Capacity.Ga. Comp. R. & Regs. R. 672-5-.12
O.C.G.A. §§ 32-2-2, 50-13-4.
Original Rule entitled "Effect of Subcontracting on Contractor's Capacity" adopted. F. Aug. 9, 1973; eff. Aug. 29, 1973.Amended: F. Dec. 22, 1976; eff. Jan. 11, 1977.Repealed: New Rule, same title adopted. F. Oct. 23, 2000; eff. Nov. 12, 2000.Amended: F. May 1, 2018; eff. May 21, 2018.