Ga. Comp. R. & Regs. 515-7-7-.11

Current through Rules and Regulations filed through June 17, 2024
Rule 515-7-7-.11 - Force Majeure

The Commission recognizes that the EDC's performance data may be influenced by factors beyond its control. Accordingly, in the event of a force majeure, as defined by Rule 12 of AGLC's Commission-approved Tariff, the EDC may file a petition for an exception with the Commission seeking to have the quarterly service quality standards and/or benchmark results modified. The EDC will also be allowed to file an expedited petition seeking immediate relief from a payment of penalties as set forth in these Rules in the event of a force majeure. In any such petition, the EDC shall have the burden of demonstrating that the benchmark was not met due to causes beyond the EDC's control and which could not have been avoided by exercise of due care. The filing of any such petition shall not stay any payments under these Rules unless otherwise ordered by the Commission.

Ga. Comp. R. & Regs. R. 515-7-7-.11

O.C.G.A. Sec. 46-4-158.1.

Original Rule entitled "Force Majeure" adopted. F. Sept. 3, 2002; eff. Sept. 23, 2002.