D.C. Mun. Regs. tit. 9, r. 9-362

Current through Register Vol. 72, No. 2, January 10, 2025
Rule 9-362 - DETERMINATION OF ASSESSED VALUE OF REAL PROPERTY WITH CONSTRUCTION IN PROGRESS
362.1

For construction in progress, sixty-five percent (65%) complete shall be based on how components of an improvement contribute to the overall base structure. A tenant finish is not a component of a structure that contributes to the overall base structure.

362.2

The following guide shall be used to estimate the percentage of completion for a single family detached residence:

PERCENTAGE OF COMPLETION

Percentage of total

Cumulative Percentage of total

Plans, permits and survey

2%

2%

Excavation, forms, water/sewage hookup

hookup

4

6

Concrete

8

14

Rough framing

21

35

Windows and exterior doors

2

37

Roof cover

3

40

Rough-in plumbing

4

44

Insulation

1

45

Rough-in electrical and mechanical

11

56

Exterior

6

62

Interior

8

70

Built-in cabinets, interior doors, trim, etc.

etc.

13

83

Plumbing

5

88

Floor covers

3

91

Built-in appliance

3

94

Light fixtures and finish hardware

2

96

Painting and decorating

4

100

100%

362.3

The following guide shall be used to estimate the percentage of completion for all other structures:

PERCENTAGE OF COMPLETION

Percentage of total

CumulativePercentage

of total

Plans, permits, and survey

2%

2%

Foundation

6

8

Slab and Frame

24

32

Exterior Walls

14

46

Roof

2

48

Electricity

5

53

Heat & Air Conditioning

15

68

Plumbing

9

77

Misc. Equip., Elevators, Etc.

2

79

Sprinklers

2

81

Interior Partitions (Studding),

Interior Finish (Lath) (Dry Wall)

(Plaster) (Tape), Carpentry & Millwork., Tiling, and Flooring

15

96

Paint

2

98

Landscape, Paving

2

100

100%

362.4

For renovations, additions that are not new structures, and other additions, the Deputy Chief Financial Officer may consider the taxpayer's submitted "Schedule of Costs" (FP 315) when determining the assessed value of the real property.

362.5

In determining the assessed value of real property where there is construction in progress and sixty-five percent (65%) of the total estimated construction is determined to be complete, the Deputy Chief Financial Officer may consider the "Schedule of Costs" (FP 315).

362.6

In considering the "Schedule of Costs," the Deputy Chief Financial Officer shall rely primarily on the Percentage of Completion Guides in §§ 362.2 and 362.3.

D.C. Mun. Regs. tit. 9, r. 9-362

Final Rulemaking published at 40 DCR 8171, 8173 (November 19, 1993)