D.C. Mun. Regs. r. 27-4726

Current through Register Vol. 71, No. 24, June 14, 2024
Rule 27-4726 - PAYMENT REQUESTS
4726.1

Requests for payment must be submitted in writing by the contractor. Payment shall not be authorized without a valid written contract.

4726.2

Contractor payment requests shall:

(a) Certify that the contractor is entitled to payment in the requested amount; and
(b) Include or attach any information necessary to demonstrate entitlement to the requested payment under the contract's terms.
4726.3

Depending on the contract's payment provisions, a payment request may consist of, for example, a statement that specified work has been completed in a satisfactory manner, documentation showing that contract deliverables have been accepted by the Office, or information detailing the reimbursable costs incurred by the contractor.

4726.4

Unless the Contracting Officer authorizes the payments, they shall not be made. A Contracting Officer's payment authorization shall not preclude the Department from seeking repayment or pursuing other remedies if it subsequently concludes that the contractor was overpaid or otherwise mispaid.

4726.5

In addition to the Contracting Officer's payment authorization, the Department's CFO or his or her designee shall certify and approve all payment requests prior to making any payment.

D.C. Mun. Regs. r. 27-4726

Notice of Emergency and Proposed Rulemaking published at 58 DC 8805 (October 14, 2011)[EXPIRED]; as amended by Notice of Final Rulemaking published at 59 DCR 985, 1011 (February 10, 2012)
Authority: The Interim Director of the Department of General Services (Department), pursuant to section 1106(a)(2) of the Procurement Practices Reform Act of 2010, effective April 8, 2011(D.C. Law 18-371; D.C. Official Code § 2-361.06(a)(2) )(2011 Repl.); sections 1025(a) and 1029 of the Department of General Services Establishment Act of 2011, effective September 14, 2011(D.C. Law 19-21; 58 DCR 6226); and Mayor's Order 2011-168, dated October 5, 2011.