D.C. Mun. Regs. r. 27-2999

Current through Register Vol. 71, No. 24, June 14, 2024
Rule 27-2999 - DEFINITIONS
2999.1

When used in this chapter, the following terms have the meanings ascribed:

Special pilot project - a short-term, carefully planned, pilot exercise designed to test and evaluate the feasibility of a new and unique District requirement or to obtain a new technology.

Director - the Director of the Office of Contracting and Procurement or the District of Columbia Chief Procurement Officer.

D.C. Mun. Regs. r. 27-2999

Final Rulemaking published at 63 DCR 9374 (7/8/2016)