Rule 27-1540 - BID EVALUATION
1540.1

The contracting officer shall determine whether a prospective contractor is responsible and whether the prices offered are reasonable.

1540.2

Prompt payment discounts shall not be considered in the evaluation of bids. However, any discount offered shall form a part of the award and shall be taken by the District if payment is made within the discount period specified by the bidder.

D.C. Mun. Regs. r. 27-1540

Final Rulemaking published at 35 DCR 1438 (February 26, 1988); as amended by Notice of Emergency and Proposed Rulemaking published at 59 DCR 3714 (March 6, 2012)[EXPIRED]; as amended by Notice of Final Rulemaking published 59 DCR 6290, 6306 (June 1, 2012)
Authority: The Chief Procurement Officer of the District of Columbia (CPO), pursuant to the authority set forth in sections 401, 402, 409, 414, 1102, and 1106 of the Procurement Practices Reform Act of 2010, effective April 8, 2011 (D.C. Law 18-371; D.C. Official Code §§ 2-354.01, 2-354.04, 2-354.14, 2-361.02 and 2-361.06 (2011 Repl.)) (Act).