D.C. Mun. Regs. r. 21-1822

Current through Register Vol. 71, No. 24, June 14, 2024
Rule 21-1822 - WELL CONSTRUCTION REQUIREMENTS: MONITORING WELL, OBSERVATION WELL, AND PIEZOMETER
1822.1

The construction of a monitoring well, observation well, or piezometer shall be conducted by a method that allows for the determination of characteristics of the geologic materials under the site, unless otherwise approved by the Department in the well construction work plan.

1822.2

A monitoring well, observation well, or piezometer's uncompleted borehole shall not penetrate to a depth greater than the depth to be monitored, and any portion of the borehole that extends to a depth greater than the depth to be monitored shall be grouted completely to prevent vertical migration of contaminants.

D.C. Mun. Regs. r. 21-1822

Final Rulemaking published at 63 DCR 13424 (10/28/2016)