D.C. Mun. Regs. tit. 15, r. 15-2905

Current through Register Vol. 71, No. 52, December 27, 2024
Rule 15-2905 - RECOVERY OF FEES AND COSTS
2905.1

Recovery of any fees and costs by the Electric Company and Electricity Suppliers shall be in accordance with D.C. Official Code Section 34-1435.

2905.2

No Electricity Supplier shall recover any compliance fee levied pursuant to D.C. Official Code Section 34-1434 from its customers without receiving prior approval from the Commission.

2905.3

Pursuant to D.C. Official Code Section 34-1435(a), the Electric Company may recover prudently incurred RPS compliance costs, including REC purchases and any compliance fees.

2905.4

Electric Company compliance costs for Standard Offer Service (SOS) shall be considered prudent if SOS energy suppliers are selected through a competitive bid process and the cost of complying with the RPS is included in the supplier's bid prices.

2905.5

Any cost recovery approved by the Commission may be in the form of a non-bypassable surcharge to current applicable customers and shall be disclosed on their bills.

D.C. Mun. Regs. tit. 15, r. 15-2905

Notice of Final Rulemaking published at 55 DCR 000561 (January 18, 2008); as amended by Notice of Final Rulemaking published at 59 DCR 2313, 2323 (March 23, 2012); amended by Final Rulemaking published at 65 DCR 13506 (12/14/2018); amended by Final Rulemaking published at 67 DCR 11091 (9/18/2020); amended by Final Rulemaking published at 71 DCR 3262 (3/22/2024)
Authority: The Public Service Commission of the District of Columbia (Commission) pursuant to section 34 -802 of the D.C. Official Code and in accordance with section 2 -505 of the D.C. Official Code.