D.C. Mun. Regs. tit. 15, r. 15-2105

Current through Register Vol. 72, No. 2, January 10, 2025
Rule 15-2105 - ALTERNATIVE OVERHEAD TRANSMISSION LINE ROUTES
2105.1

The description of each alternative route considered for the transmission line shall include the following:

(a) An estimate of the capital and annual operating cost of each alternative route; and
(b) A statement of the reason why each alternative route was rejected.

D.C. Mun. Regs. tit. 15, r. 15-2105

Final Rulemaking published at 51 DCR 8643 (September 3, 2004)