The fees for a Certificate of Occupancy shall be computed as specified in this section.
The fees for filing a Certificate of Occupancy shall be twenty dollars ($20).
Subsequent to administrative review and upon approval of an application for a new Certificate of Occupancy, the following computed fee shall be paid:
(a) | Up to 5,000 sq. ft. 5001 sq. ft. to 50,000 sq. ft.for all sq. ft. above 5,001 sq. ft.; | $ 27.00 27 plus .004 |
(b) | 50,000 sq. ft. to 100,000 sq. ft.for all sq. ft. above 50,001 sq. ft.; and | 207 plus .003 |
(c) | 100,001 sq. ft. and upfor all sq. ft. above 100,001 sq. ft. | 357 plus .0013 |
Where the lot or parcel upon which the building stands is also devoted to the use requested, or there is no building on the lot or parcel, the fee for a Certificate of Occupancy for the land shall be computed as cited in this section, multiplying the square footage of the lot occupied by the building by the appropriate fee.
D.C. Mun. Regs. tit. 14, r. 14-1411