Strike Chapter 9 of the International Green Construction Code in its entirety and insert new Chapter 9 in the Green Construction Code in its place to read as follows:
General. Where application is made for construction as described in this section, the registered design professional in responsible charge or approved agency shall perform commissioning during construction as required by Table 903.1 and by Administrative Bulletins. The approved agency shall be qualified and shall demonstrate competence, to the satisfaction of the code official, for the commissioning of the particular type of construction or operation in accordance with the qualification requirements set forth in Administrative Bulletins. The registered design professionalin responsiblecharge and engineers of record involved in the design of the project are permitted to act as the approved agency provided those personnel meet the qualification requirements set forth in the Green Building Program Manual to the satisfaction of the code official.
Preliminary commissioning report requirement. The approved agency shall keep records of the commissioning required by Table 903.1.
The approved agency shall furnish commissioning reports to the owner and the registereddesign professional in responsible charge and, upon request, to the code official. Reports shall indicate that work was or was not completed in conformance to approved construction documents. Discrepancies shall be brought to the immediate attention of the contractor for correction. Where discrepancies are not corrected, they shall be brought to the attention of the owner,code official and to the registered design professional in responsiblecharge prior to the completion of that phase of the work. Prior to the final inspection, a Preliminary Commissioning Report shall be provided to the owner and a copy shall be made available to the code official upon request.
Final commissioning report requirement. A Final Commissioning Report shall be provided to the owner within 180 days after the date of issuance of the first certificate of occupancy for occupiable space in a story above grade plane, and a copy shall be made available to the code official upon request.
TABLE 903.1
COMMISSIONING PLAN
CONSTRUCTION OR SYSTEM REQUIRING VERIFICATION | PREOCCUPANCY | METHOD | OCCURRENCE Preoccupancy | SECTION/ REFERENCED STANDARD |
Chapter 4: Site Development and Land Use | ||||
Landscape irrigation systems | X | Field-inspection | Installation | Section 614 of the Plumbing Code |
Stormwater management system operation | None | Field-inspection | Installation | 21 DCMR (Water and Sanitation), Chapter 5 (Water Quality and Pollution) |
Site lighting | X | Testing and report | Installation | 409 |
Chapter 6: Energy | ||||
Energy consumption, monitoring, targeting and reporting | ||||
a. Monitoring system | X | Inspection and verification | During construction and prior to occupancy | 603 |
b. Calibration | X | Testing and review and evaluation or test reports | During commissioning | 603 |
Mechanical systems completion | ||||
a. Air system balancing - provide the means for system balancing | X | Inspection and verification | During construction and prior to occupancy | 611.1.2.1 and through reference to Energy Conservation Code |
b. Hydronic system balancing - provide means for system balancing | X | Inspection and verification | During construction and prior to occupancy | 611.1.2.2 and through reference to Energy Conservation Code |
c. Mechanical system manuals - construction documents to require O&M manual | X | Verification of construction documents | Plan review | 611.1.5.2 |
Mechanical systems | ||||
a. Commissioning required and noted in plans and specifications | X | Verification of construction documents | Plan review | 611.1 |
b. Documentation of required commissioning outcomes | X | Verification with the building owner | Subsequent to completion of all commissioning activities | 611.1 |
c. Preparation and availability of a commissioning plan | X | Verification with the RDP or commissioning agent | Between plan review and commissioning initiation | 611.1.1 |
d. Balance HVAC systems (both air and hydronic) | X | HVAC system installer/contractor or commissioning agent | After installation of HVAC systems and prior to occupancy | 611.1.2 |
e. Functional performance testing of HVAC equipment | X | HVAC system installer/contractor or commissioning agent | After installation of HVAC systems and prior to occupancy | 611.1.3 |
f. Functional performance testing of HVAC controls and control systems | X | HVAC system installer/contractor or commissioning agent | After installation of HVAC systems and prior to occupancy | 611.1.3.2 |
g. Preparation of preliminary commissioning report | None | HVAC system installer/contractor or commissioning agent | None | 611.1.4 |
h. Acceptance of HVAC systems and equipment/system verification report | None | Building owner | None | 611.1.4.1 |
i. Preparation and distribution of final HVAC system completion. Documentation that construction documents require drawings, manuals, balancing reports and commissioning report be provided to the owner and that they have been provided | None | RDP, contractor or commissioning authority | None | 611.1.5 |
Chapter 6: Lighting | ||||
Verification of lamp | X | Field inspection | Final inspection | 611.3 |
Verification of ballast | X | Field inspection | Final inspection | 611.3 |
Lighting Controls | ||||
a. Installation | X | Field inspection | Final inspection | 611.3.2 |
b. Calibration | X | System installer/Contractor or commissioning agent | Final inspection | 611.3 |
Chapter 7: Water Resource Conservation, Quality and Efficiency | ||||
Cooling tower performance | - | - | - | 703.7.7 |
Metering | X | - | - | 705.1.1 |
Chapter 8: Indoor Environmental Quality and Comfort | ||||
Air-handling system access | X | Field inspection and verification | During construction and prior to occupancy | 802.2 |
Air-handling system filters | X | Field inspection and verification | During construction and prior to occupancy | 802.3 |
For SI: 1 square foot = 0.0929 m2. |
D.C. Mun. Regs. tit. 12, r. 12-K903