7 Del. Admin. Code § 7103-121.0

Current through Register Vol. 28, No. 3, September 1, 2024
Section 7103-121.0 - Site Inspection and Concurrence

The Project Development Report is submitted for Department review along with a request for general site concurrence.Upon receipt of the report, a Department representative will inspect the selected site(s) and a written site concurrence or denial letter will be sent to the applicant. Upon receipt of a site concurrence the applicant may submit a permit application. Site concurrences for land treatment of sludges are valid for one year.

7 Del. Admin. Code § 7103-121.0