Section 1002-G-3.0 - Hearing

The Commission will, at its earliest reasonable convenience, schedule a hearing on the utility's request for effective new tariffs. The Commission Staff shall review the utility's calculations, repricing the various expense items at current rates and advise the Commission if such have been accurately performed. If the Commission Staff advises the Commission that such repricing has been accurately performed, the Commission may, at its option, hear and review the utility's request for an expedited rate change at a regularly scheduled public meeting of the Commission. The burden of proof at such hearing shall be as set forth in 26 Del.C. § 307.