26 Del. Admin. Code § 1002-B-1.0

Current through Register Vol. 27, No. 12, June 1, 2024
Section 1002-B-1.0 - Instructions
1.1 Prefiling Announcement

In order for the Commission to schedule its future workload in an efficient manner, every public utility shall file with the Commission a Notice of Intent to file a general rate increase application not less than two (2) months prior to filing its application or notice of increase. If a regulated company cancels, changes or delays a proposed general rate increase application previously reported to the Commission, an amended report must be filed promptly reflecting such change of plans.

1.2 Test Year
1.2.1 The test year is the actual historical period of time for which operating and financial data will be required. The test year must include the actual "Per Books" results of operation for a twelve month period ending no more than four months prior to the filing of the application for increased rates. In addition, the twelve-month period must end no later than 7 months prior to the filing of the application, but no sooner than one month after the final closing of the test year (post reversal of accrual entries), so that actual expenditures are reflected in the books of account. For example, if the actual results of operations for the twelve months ending March 30, 200x are used for purposes of the test year, the application must be filed no sooner than April 30, 200x, but no later than October 31, 200x.
1.2.2 It is suggested but not required that the test year selected correspond with the company's financial year.
1.2.3 The test year may be adjusted to reflect changes that are known and measurable at the time of the filing.
1.3 Due Date

The information required in subsequent sections of Part B is to be filed with the Commission at the time of the utility's application for an increase in rates.

1.4 Testimony and Exhibits

If the utility plans to submit prepared testimony and exhibits, they must be filed coincident with the filing of the application for rate relief.

1.5 Penalty for Non-Compliance

The Commission Staff will review all filings for compliance with the format and instructions furnished herein and, within fifteen (15) days after the date of filing, specifically identify any non-compliance with such format and instructions, and immediately request the Commission Secretary to promptly notify the utility of the alleged defects in compliance. Following such notification by the Commission's Secretary, the utility shall have fifteen (15) days within which to correct the alleged defects; and only upon the utility's filing of the corrected application shall such application be deemed filed with the Commission for the purposes contemplated under the Public Utilities Act. In the event the alleged defects are not corrected within the time provided hereunder, Staff may move the Commission to reject the utility's application for non-compliance with these Minimum Filing Requirements.

Nothing in this section 1.5 shall prevent a utility from filing an application in draft form for Staff's informal review and approval without prejudice, such informal review and approval not to be unreasonably withheld by Staff, nor shall section 1.5 affect or delay the filing date, for the purposes contemplated under the Public Utilities Act, of rate applications that comply with the format and instructions furnished herein, or whose non-compliance with such format and instructions is deemed minor by the Commission or its Staff.

1.6 General Guidelines
1.6.1 Schedules shown are for illustrative purposes and may be modified to fit the individual company as long as the data intent is complied with. The burden of proof remains by Statute on the utility; therefore, if applicant utility believes that additional information is necessary to support its case or is proposing a position which requires a departure from the basic schedules, the utility should supplement the standard filing requirements as required to support its position.
1.6.2 The Commission may require utilities to supply information to supplement these minimum requirements during the course of the Staff investigation of a specific case. The utility will be required to provide a duplicate copy of any such information requested by Staff to all intervenors to the proceeding as directed by the Commission. It is, however, the intent of the Commission in establishing minimum filing requirements to minimize the subsequent interrogatories and data requests.
1.6.3 All schedules submitted to the Commission shall be typed and shall contain the name of the person responsible for the preparation of the data.
1.6.4 Supportive work papers must be made available for Staff inspection upon request subsequent to the filing.
1.6.5 If required data has been previously filed, it may be incorporated by reference.
1.6.6 All data, statements and exhibits filed pursuant to these minimum filing requirements shall be identified by paragraph designation for which they are submitted.

26 Del. Admin. Code § 1002-B-1.0

27 DE Reg. 890 (5/1/2024) (Final)