Conn. Agencies Regs. § 29-232-5

Current through November 7, 2024
Section 29-232-5 - Notification of inspection

The owner or user shall prepare each boiler for internal inspection and shall prepare for and apply a hydrostatic pressure test when required on the date specified by an inspector, which date shall be not less than seven days after the date of notification.

Conn. Agencies Regs. § 29-232-5

Effective August 25, 1987