Section 22a-39-5.6.e - Public hearings

All public hearings shall commence not sooner than thirty (30) days nor later than sixty (60) days after the receipt of a complete application. Notice of the hearing shall be published at least once not more than thirty (30) days and not fewer than ten (10) days before the date set for the hearing in a newspaper having a general circulation in each town where the affected wetlands or water courses are located. All applications, maps, and documents relating to this hearing shall be open for public inspection at the Office of the Clerk of the municipality wherein the affected inland wetland or water course is located, or at the Department. Notices of hearings shall be sent to the applicant, adjacent property owners, all known interested parties and groups, and to chief executive officers of the town wherein the wetland or water course lies.