Conn. Agencies Regs. § 16-11-139

Current through June 15, 2024
Section 16-11-139 - Supporting data

A petition required by section 16-11-137 or 16-11-138 shall be accompanied by the following:

(1) A map indicating the route of the line and the location of the circuits. The map shall show the points at which such electric lines will cross over or under public highways, and the circuits, tracks and other facilities of municipalities and other utilities;
(2) copies of letters from each railroad, municipality or other utility affected. stating that it has been notified of the details of the proposed line and that it offers no objection to the method or manner of construction.

Conn. Agencies Regs. § 16-11-139