4 Colo. Code Regs. § 723-3-3101

Current through Register Vol. 47, No. 11, June 10, 2024
Section 4 CCR 723-3-3101 - Certificate of Public Convenience and Necessity for Service Territory
(a) A utility seeking authority to provide service in a new service territory shall file an application pursuant to this rule. A utility cannot provide service to a new geographic area without authority from the Commission, unless the utility extends its facilities and service:
(I) within a city and county or city or town within which the utility has lawfully commenced operations;
(II) into territory contiguous to the utility's facility, line, plant, or system that is not served by a public utility providing the same commodity or service; or
(III) within or to territory already served by the utility and the extension is necessary in the ordinary course of business.
(b) An application for certificate of public convenience and necessity to provide service in a new territory shall include, in the following order and specifically identified, the following information, either in the application or in appropriately identified attachments:
(I) the information required in paragraphs 3002(b) and 3002(c);
(II) a statement of the facts (not conclusory statements) relied upon by the applying utility to show that the public convenience and necessity require the granting of the application;
(III) a description of the type of utility service to be rendered and a description of the area sought to be served;
(IV) a map showing the specific geographic area that the applying utility proposes to serve. If the applying utility intends to phase in service in the territory over time, specific areas and proposed in-service dates shall be included. The map shall describe the geographic areas in section, township, and range convention;
(V) a statement describing in detail the extent to which the applying utility is an affiliate of any other utility which holds authority duplicating in any respect the territory sought;
(VI) a statement of the names of public utilities and other entities of like character providing similar service in or near the area involved in the application; and
(VII) a copy of a feasibility study for the proposed area to be served, which shall at least include estimated investment, income, and expense. An applying utility may request that its most recent audited balance sheet, income statement, statement of retained earnings, and statement of cash flows be submitted in lieu of a feasibility study.

4 CCR 723-3-3101

38 CR 17, September 10, 2015, effective 9/30/2015
39 CR 06, March 25, 2016, effective 4/14/2016
39 CR 08, April 25, 2016, effective 5/15/2016
40 CR 22, November 25, 2017, effective 12/15/2017
42 CR 03, February 10, 2019, effective 3/2/2019
42 CR 07, April 10, 2019, effective 4/30/2019
42 CR 09, May 10, 2019, effective 5/30/2019
43 CR 08, April 25, 2020, effective 5/15/2020
43 CR 12, June 25, 2020, effective 7/15/2020
43 CR 20, October 25, 2020, effective 11/14/2020
44 CR 13, July 10, 2021, effective 7/30/2021
44 CR 24, December 25, 2021, effective 1/14/2022
45 CR 18, September 25, 2022, effective 10/15/2022
46 CR 02, January 25, 2023, effective 2/14/2023