Current through Register Vol. 47, No. 20, October 25, 2024
Section 3 CCR 718-1-21 - New installations and modifications21.1Definitions.21.1.1New installation. "New Installation" means any passenger tramway installation not previously licensed and shall include both new and relocated passenger tramways (also reference Rules 1.2.4.2 and 1.2.4.3).21.1.2Major tramway modification. "Major Tramway Modification" means any modification to a passenger tramway which alters its verified design or verified construction and which results in a substantive change: (a) In design speed of the system; or(b) In capacity by changing the number of carriers, spacing of carriers, or load capacity of carriers; or(c) In the path of the rope; or(d) In the type of brakes and/or backstops or components thereof; or(e) In structural arrangements; or(f) In power or type of prime mover or auxiliary engine; or(g) To control system logic. Design and construction verifications are required. A major tramway modification may be deemed a new installation by the Board and current requirements shall be applicable (reference Rule 1.2.4.4).
21.1.3Minor modification. "Minor Modification" means any modification, addition, or deletion to a passenger tramway which does not meet the criteria of a major modification but which results in a significant change in the tramway's verified design or verified construction and materially affects its integrity, operation or control. A design verification is required, however, no construction verification is required. A minor modification may be considered a major modification at the discretion of the Board. If the authority appointed by the Board disagrees with the classification of the modification as "minor", the matter may be referred to the Board for a final decision.21.1.4Minor alteration. "Minor Alteration" means any other addition or deletion to a passenger tramway which does not meet the criteria of a major or minor modification or one for one replacement, and which does not materially affect the tramway's integrity, operation or control. No design or construction verification is required. A minor alteration may be considered a minor modification or a major modification at the discretion of the Board.21.1.5One for one replacement. "One for One Replacement" means the replacement of a component with an equal component. A one for one replacement shall be considered as normal maintenance and not as a modification. No design or construction verification is required.21.2Procedures prior to public operation for new and relocated Installations.21.2.1Submittal of notice of new or relocated installation. Before construction of the new or relocated installation begins, the area operator shall give notice of such activity to the Board on the required forms and include the appropriate fee.21.2.2Acknowledgment of new or relocated installation. Upon receipt of the notice, the Board shall send an acknowledgment of such to the area operator together with the appropriate forms and requirements to complete the procedure as set forth in these Rules and regulations.21.2.3Submittal of request for exception. If the area operator proposes to depart from these Rules and regulations, a request for exception must be made in writing by the area operator as set forth in Rule 1.2.3.21.2.4Exception request procedure. Within thirty days after receipt of the request for exception as provided for in 21.2.3, the Board shall notify the area operator in writing of its action on the requested exception. If the Board denies or limits the requested exception, the Board's notification shall set forth the reasons for such action. Within sixty (60) days of the mailing of such notification, the area operator may appeal the Board's decision as provided for in Article 4 of Title 24 of the Colorado Revised Statutes.21.2.5Submittal of verification of design. Before construction of the new installation is begun, the Professional Engineer in responsible charge of the design shall verify to the Board on the appropriate forms that the passenger tramway design conforms to all rules and regulations of the Board. Copies of such designs, plans and specifications shall be submitted with this written verification.21.2.6Submittal of acceptance test request. Acceptance tests will be scheduled by the Board on a first come, first served basis. At least thirty (30) days before a requested acceptance test, the area operator shall notify the Board of a projected date for the required acceptance test. Upon receipt of such notification the Board shall establish a tentative acceptance test date for such passenger tramway and shall notify the area operator of the same. If the projected date changes the area operator shall immediately notify the Board of same, and the Board shall reschedule the acceptance test. No later than three (3) days before the date of the acceptance test, the area operator shall notify the Board that the passenger tramway is completed and ready for testing. The area operator shall verify to the Board that the required hours of continuous operation have been accomplished in accordance with 2.1.1.11.2 or 3.1.1.11.2 or 4.1.1.11.2. Upon receipt of such timely notifications, the initial inspection and acceptance test shall proceed as scheduled.21.2.7Submittal of acceptance test procedure. At least thirty (30) days before the scheduled acceptance test date, the area operator shall submit an acceptance test procedure which was prepared by the Professional Engineer in responsible charge of the design (see 2.1.1.11, 3.1.1.11, 4.1.1.11, 5.1.1.11, 6.1.1.11, 8.1.1.11, or 2.1.1.11 ANSI B77.2-2004) for approval by the Board or the authority appointed by the Board.21.2.8Submittal of verification of concrete construction. After the new installation or relocation is completed and before the initial inspection is conducted, and before the acceptance test is observed, the Professional Engineer in responsible charge of the tramway construction shall verify to the Board on the appropriate form that the foundations, soils and concrete test samples have been inspected and completed according to the design, plans and specifications for such work. This document shall be required prior to the acceptance test.21.2.9Submittal of verification of acceptance test. For new or modified ropeways, a qualified engineer shall witness the acceptance test and certify to the owner that the ropeway was in compliance with the CPTSB Rules and Regulations based on the successful completion of acceptance inspection (X.1.1.11.2). Any deficiencies to the acceptance test shall be included in the acceptance test report by the Board Inspector (21.2.12).
21.2.10Submittal of as-built drawings and additional documents. Prior to or during the acceptance test, the "As-Built" designs, plans, specifications and drawings signed and sealed by the design engineer shall be submitted to the Board. Within thirty days after the acceptance test, the authority appointed by the Board shall notify the area operator of any additional documents which must be submitted.
21.2.11Inspection and acceptance test. All inspections and acceptance tests shall be according to these rules and regulations. Items failing to pass the acceptance test shall be retested if so directed by the Board.21.2.12Submittal of verification of initial inspection and acceptance test. The Board inspector shall report to the Board the results of the Acceptance Test and any deficiencies.21.3Procedures prior to public operation for tramways with major tramway modifications. In addition to the applicable requirements of Section 20 and Rule 1.2, the following procedure shall be completed prior to public operation of the passenger tramway.21.3.1Submittal of notice of modification. Before the major tramway modification commences, the area operator shall give notice of such activity to the Board on the required forms and include the appropriate fee.21.3.2Acknowledgment of major tramway modification. Upon receipt of the notice, the Board shall send an acknowledgment of such to the area operator together with the appropriate forms and requirements to complete the procedure as set forth in these rules and regulations.21.3.3Submittal of request for exception. If the area operator proposes to depart from these rules and regulations, a request for exception must be made in writing by the area operator as set forth in Rule 1.2.3.21.3.4Exception request procedure. Within thirty days after receipt of the request for exception as provided for in 21.3.3, the Board shall notify the area operator in writing of its action on the request. If the Board denies or limits the requested exception, the Board's notification shall set forth the reasons for such action. The area operator may appeal the Board's decision as provided for in Article 4 of Title 24 of the Colorado Revised Statutes.21.3.5Submittal of verification of design. Before construction of the major tramway modification is begun, the Professional Engineer in responsible charge of the design of the Tramway major modification shall verify to the Board on the appropriate forms that the design, plans and specifications for the major tramway modification conforms to all rules and regulations of the Board and is compatible with the existing Tramway design. Copies of such designs, plans and specifications shall be submitted with this written verification.21.3.6Submittal of acceptance test request. Acceptance tests will be scheduled by the Board on a first come, first served basis. At least thirty days before a requested acceptance test, the area operator shall notify the Board of a projected date for the acceptance test. Upon receipt of such notification, the Board shall establish a tentative acceptance test date for such passenger tramway and shall notify the area operator of the same. If the projected date changes, the area operator shall immediately notify the Board of same and the Board shall reschedule the acceptance test. No later than three days before the date of the acceptance test, the area operator shall notify the Board that the passenger tramway modification is completed and ready for testing.21.3.7Submittal of acceptance test procedure. At least thirty days before the scheduled acceptance test date, the area operator shall submit an acceptance test procedure which was prepared by the Professional Engineer in responsible charge of the design of the major tramway modification for approval by the Board or the authority appointed by the Board. The acceptance test procedure shall take into consideration the modification which was made to the passenger tramway and should be tailored to test the critical components of said modification.21.3.8Submittal of verification of concrete construction. After the major modification is completed and before the initial inspection is conducted, and before the acceptance test is observed, the Professional Engineer in responsible charge of the tramway construction shall verify to the Board on the appropriate form that the foundations, soils and concrete test samples have been inspected and completed according to the design, plans and specifications for such work. This document shall be required prior to the acceptance test.21.3.9Submittal of verification of acceptance test. For major modifications, a qualified engineer shall witness the acceptance test and certify to the owner that the ropeway was in compliance with the CPTSB Rules and Regulations based on the successful completion of acceptance inspection (X.1.1.11.2). Any deficiencies to the acceptance test shall be included in the acceptance test report by the Board Inspector (21.3.12).
21.3.10Submittal of as-built drawings and additional documents. Prior to or during the acceptance test, the "As-Built" designs, plans, specifications and drawings signed and sealed by the design engineer shall be submitted to the Board. Within thirty days after the acceptance test, the authority appointed by the Board shall notify the area operator of any additional documents which must be submitted
21.3.11Inspection and acceptance test. All inspections and acceptance tests shall be according to these rules and regulations. Items failing to pass the acceptance test shall be retested if so directed by the Board.21.3.12Submittal of verification of initial inspection and acceptance test. The Board inspector shall report to the Board the results of the Acceptance Test and any deficiencies.21.4Procedures for tramways with minor modifications.21.4.1Submittal of notice of modification. Before the minor modification commences, the area operator shall give notice of such activity to the Board on the required forms.21.4.2Acknowledgment of minor modification. Upon receipt of the notice, the Board shall send an acknowledgment of such to the area operator together with the appropriate forms and requirements to complete the procedure as set forth in these rules and regulations.21.4.3Documentation of minor modifications. The area operator shall keep a log documenting all minor modifications made to each of its passenger tramways. Such log shall be readily available for inspection by the Board or designated representatives of the Board and shall contain at a minimum the following information: (a) Tramway name or other means of identification;(b) Name of design engineer;(c) Verification of design engineer on form approved by the Board;(d) Date of modification;(e) Purpose of modification;(f) Description of modification;(g) Names of personnel performing such modification;(h) Date of modification review and acceptance by area operator or its authorized agent. Each area operator's log of minor modifications shall be readily available to the Board's inspectors during every inspection.
21.5Documentation of Minor Alterations. The area operator shall keep a log documenting all minor alterations made to each of its passenger tramways. Such log shall be readily available for inspection by the Board or designated representatives of the Board and shall contain at a minimum the following information:(a) Tramway name or other means of identification;(c) Purpose of alteration;(d) Description of alteration;(e) Names of personnel performing such alteration;(f) Date of alteration review and acceptance by area operator or its authorized agent. Each area operator's log of minor alterations shall be readily available to the Board's inspectors during every inspection.
37 CR 11, June 10, 2014, effective 7/1/201437 CR 18, September 25, 2014, effective 11/1/201438 CR 06, March 25, 2015, effective 5/1/201538 CR 18, September 25, 2015, effective 11/1/201540 CR 06, March 25, 2017, effective 5/15/201740 CR 11, June 10, 2017, effective 7/1/201742 CR 05, March 10, 2019, effective 4/15/201946 CR 12, June 25, 2023, effective 7/15/2023