Section 2 CCR 601-10-5.01 - Selection of Projects
5.01.1 Any project that is constructed by CDOT with its own forces shall meet one or more of the following criteria:
(a) Projects for which the expenditure of funds is reasonably expected to be less than one hundred fifty thousand dollars in the aggregate for the fiscal year,
(b) Projects that cannot be defined as to start or stop time,
(c) Projects that cannot be defined as to geographical limits,
(d) Projects that cannot be defined as measurable units of Work, or
(e) Projects on which the nature of the Work is such that delays in progressing with the Work would endanger the public health, welfare or safety.