2 Colo. Code Regs. § 601-10-2.01

Current through Register Vol. 47, No. 11, June 10, 2024
Section 2 CCR 601-10-2.01 - Prequalification Application
2.01.1 A Contractor who wishes to submit a Bid for a Public Project is required to file a Prequalification application with the CDOT Contracts and Market Analysis Branch Manager or designee. Any new application or renewal application may be submitted not less than seventeen calendar days prior to the opening of any Bid for projects on which the Contractor desires to submit a Bid, unless the Branch Manager or designee grants an exception in writing based on a showing of reasonable cause. A letter from the Department approving or denying an applicant's Prequalification shall be sufficient written evidence of the Department granting an exception to the requirement that an application be submitted seventeen calendar days prior to a bid opening.
2.01.2 A joint venture may apply for Prequalification in the name of the joint venture or each member may apply for Prequalification separately and then request application for Prequalification as a joint venture if all members are successful in previously becoming prequalified. A joint venture will be considered prequalified to the highest financial level of Prequalification of any of the individual parties to the venture. Affiliates are prohibited from submitting Bids for the same Public Project.
2.01.3 Any application for Special Prequalification required under an Invitation for Bids shall be submitted and will be considered in accordance with the terms, conditions, procedures and time frame specified in the Invitation for Bids.
2.01.4 CDOT may charge a reasonable fee, not to exceed the cost of processing Prequalification applications, to any Contractor requesting Prequalification.

2 CCR 601-10-2.01

41 CR 17, September 10, 2018, effective 9/30/2018