2 Colo. Code Regs. § 404-1-911

Current through Register Vol. 47, No. 20, October 25, 2024
Section 2 CCR 404-1-911 - CLOSURE OF OIL AND GAS FACILITIES
a. Operators will close all Oil and Gas Facilities, including Drilling Pits and Cuttings Trenches, in accordance with an approved Form 27.
(1) Operators will obtain the Director's approval of the Form 27 prior to conducting any investigation or closure operations.
(2) The Form 27 will include a description of the proposed investigation and Remediation activities pursuant to Rule 913.
(3) Operators will close and remediate Emergency Pits as soon as the initial phase of emergency response operations is complete or any process Upset Conditions are controlled.
(4) Oil and Gas Facility closure pursuant to this Rule 911.a will be at the time of final site closure, Plugging and Abandonment, or decommissioning, unless the Director determines that a substantive change to the site requires a Form 27, or a reportable Spill or an historic impact is discovered during facility operation or removal.
b.Discovery of a Spill or Release During Closure. If an Operator discovers a Spill or Release during closure operations, the Operator will report the Spill or Release on a Form 19, Spill/Release Report, pursuant to Rule 912.
c.Pit Closure.
(1)Pit Evacuation. Operators will treat or dispose of E&P Waste pursuant to Rule 905 prior to backfilling and site Reclamation.
(2) Operators will collect a sufficient number of representative samples from locations beneath a Pit to demonstrate that no leakage of managed fluids has occurred. Operators will ensure that any soil left in place meets the cleanup concentrations listed in Table 915-1.
(3)Liner Disposal.
A.Synthetic Liner Disposal.Operators will remove and dispose of synthetic liners pursuant to all state and federal requirements for Solid Waste Disposal.
B.Constructed Soil Liners. Operators may remove constructed soil liner material for treatment or disposal. Alternatively, if an Operator leaves the constructed soil liner material in place, the Operator will rip the material and mix it with native soils in a manner to alleviate compaction and prevent an impermeable barrier to infiltration and Groundwater flow. Operators will demonstrate that the resulting material meets cleanup concentrations for contaminants of concern listed in Table 915-1.

2 CCR 404-1-911

37 CR 16, August 25, 2014, effective 9/30/2014
38 CR 01, January 10, 2015, effective 2/14/2015
38 CR 03, February 10, 2015, effective 3/2/2015
38 CR 07, April 10, 2015, effective 4/30/2015
38 CR 16, August 25, 2015, effective 9/14/2015
39 CR 04, February 25, 2016, effective 3/16/2016
41 CR 05, March 10, 2018, effective 4/1/2018
41 CR 06, March 25, 2018, effective 5/1/2018
41 CR 23, December 10, 2018, effective 12/30/2018
42 CR 02, January 25, 2019, effective 2/14/2019
42 CR 17, September 10, 2019, effective 9/30/2019
42 CR 24, December 25, 2019, effective 1/14/2020
43 CR 17, September 10, 2020, effective 9/30/2020
43 CR 13, July 10, 2020, effective 11/2/2020
43 CR 24, December 25, 2020, effective 1/15/2021
45 CR 07, April 10, 2022, effective 4/30/2022
45 CR 09, May 10, 2022, effective 5/30/2022
45 CR 13, July 10, 2022, effective 7/30/2022