2 Colo. Code Regs. § 404-1-606

Current through Register Vol. 47, No. 20, October 25, 2024
Section 2 CCR 404-1-606 - EQUIPMENT, WEEDS, WASTE, AND TRASH REQUIREMENTS
a. The storage, placement, or maintenance of equipment, vehicles, trailers, commercial products, Chemicals, drums, totes, Containers, materials, and all other supplies not necessary for use on an Oil and Gas Locations is prohibited.
(1) This prohibition applies to the Operator and all contractors.
(2) An Operator may request a variance pursuant to Rule 502 for a Surface Owner to use portions of the Oil and Gas Location, provided such use does not interfere with safe operations, access to equipment, Reclamation requirements, or emergency response capabilities. Such use cannot cause degradation to the site.
(3) This prohibition does not apply to emergency response trailers and associated equipment staged on an Oil and Gas Location for emergency response purposes.
b. No maintenance of equipment or vehicles is permitted at an Oil and Gas Location unless immediately necessary to allow for the continuation of active Oil and Gas Operations.
c. Oil and Gas Locations will be kept free of all Undesirable Plant Species.
d.Trash.
(1) Operators will properly dispose of all trash, rubbish, and other waste materials as non-hazardous/non-E&P solid waste, pursuant to Rule 906.c.
(2) No trash, waste, rubbish, or other materials will be burned or buried at an Oil and Gas Location.
(3) All trash, rubbish, and other waste material will be properly contained until removed from the Oil and Gas Location. At no time will trash, debris, or rubbish be placed or remain on the ground.
A. Appropriate Containers are Containers that prevent leakage of Fluids, and are capable of containing waste materials in all weather conditions.
B. Appropriate Containers will be designed, maintained, and operated to exclude wildlife.

2 CCR 404-1-606

37 CR 16, August 25, 2014, effective 9/30/2014
38 CR 01, January 10, 2015, effective 2/14/2015
38 CR 03, February 10, 2015, effective 3/2/2015
38 CR 07, April 10, 2015, effective 4/30/2015
38 CR 16, August 25, 2015, effective 9/14/2015
39 CR 04, February 25, 2016, effective 3/16/2016
41 CR 05, March 10, 2018, effective 4/1/2018
41 CR 06, March 25, 2018, effective 5/1/2018
41 CR 23, December 10, 2018, effective 12/30/2018
42 CR 02, January 25, 2019, effective 2/14/2019
42 CR 17, September 10, 2019, effective 9/30/2019
42 CR 24, December 25, 2019, effective 1/14/2020
43 CR 17, September 10, 2020, effective 9/30/2020
43 CR 13, July 10, 2020, effective 11/2/2020
43 CR 24, December 25, 2020, effective 1/15/2021
45 CR 07, April 10, 2022, effective 4/30/2022
45 CR 09, May 10, 2022, effective 5/30/2022
45 CR 13, July 10, 2022, effective 7/30/2022