2 Colo. Code Regs. § 404-1-418

Current through Register Vol. 47, No. 20, October 25, 2024
Section 2 CCR 404-1-418 - FORM 21, MECHANICAL INTEGRITY TEST
a. Results of all mechanical integrity tests, including tests that show a lack of integrity, will be submitted on Form 21, Mechanical Integrity Test, within 30 days after the test.
b. A mechanical integrity test that shows the Well lacks integrity is considered a failed test.
c. The Form 21 will be completely filled out except for Part II, which is required only for injection Wells. An original copy of the pressure chart will be submitted with every Form 21.

2 CCR 404-1-418

37 CR 16, August 25, 2014, effective 9/30/2014
38 CR 01, January 10, 2015, effective 2/14/2015
38 CR 03, February 10, 2015, effective 3/2/2015
38 CR 07, April 10, 2015, effective 4/30/2015
38 CR 16, August 25, 2015, effective 9/14/2015
39 CR 04, February 25, 2016, effective 3/16/2016
41 CR 05, March 10, 2018, effective 4/1/2018
41 CR 06, March 25, 2018, effective 5/1/2018
41 CR 23, December 10, 2018, effective 12/30/2018
42 CR 02, January 25, 2019, effective 2/14/2019
42 CR 17, September 10, 2019, effective 9/30/2019
42 CR 24, December 25, 2019, effective 1/14/2020
43 CR 17, September 10, 2020, effective 9/30/2020
43 CR 13, July 10, 2020, effective 11/2/2020
43 CR 24, December 25, 2020, effective 1/15/2021
45 CR 07, April 10, 2022, effective 4/30/2022
45 CR 09, May 10, 2022, effective 5/30/2022
45 CR 13, July 10, 2022, effective 7/30/2022