2 Colo. Code Regs. § 404-1-416

Current through Register Vol. 47, No. 20, October 25, 2024
Section 2 CCR 404-1-416 - FORM 5A, COMPLETED INTERVAL REPORT
a. The Operator will submit the Form 5A, Completed Interval Report for a formation within 30 days after the following operations:
(1) Any Stimulation or re-stimulation;
(2) Any Productivity Test (successful or not), if there is no Stimulation;
(3) Any reperforation or change in the perforated interval if there is no Stimulation;
(4) Commingling with another formation;
(5) Temporary abandonment; or
(6) Permanent abandonment of the formation if the Well is not to be abandoned.
b. The Operator will report the details of any Stimulation performed including, but not limited to, Hydraulic Fracturing Treatment and acidizing Stimulation.
c. In order to resolve completed interval information uncertainties, the Director may require an Operator to submit further information in an additional Form 5A.

2 CCR 404-1-416

37 CR 16, August 25, 2014, effective 9/30/2014
38 CR 01, January 10, 2015, effective 2/14/2015
38 CR 03, February 10, 2015, effective 3/2/2015
38 CR 07, April 10, 2015, effective 4/30/2015
38 CR 16, August 25, 2015, effective 9/14/2015
39 CR 04, February 25, 2016, effective 3/16/2016
41 CR 05, March 10, 2018, effective 4/1/2018
41 CR 06, March 25, 2018, effective 5/1/2018
41 CR 23, December 10, 2018, effective 12/30/2018
42 CR 02, January 25, 2019, effective 2/14/2019
42 CR 17, September 10, 2019, effective 9/30/2019
42 CR 24, December 25, 2019, effective 1/14/2020
43 CR 17, September 10, 2020, effective 9/30/2020
43 CR 13, July 10, 2020, effective 11/2/2020
43 CR 24, December 25, 2020, effective 1/15/2021
45 CR 07, April 10, 2022, effective 4/30/2022
45 CR 09, May 10, 2022, effective 5/30/2022
45 CR 13, July 10, 2022, effective 7/30/2022