2 Colo. Code Regs. § 404-1-310

Current through Register Vol. 47, No. 20, October 25, 2024
Section 2 CCR 404-1-310 - SUSPENDING APPROVED OIL AND GAS DEVELOPMENT PLANS

The Director may suspend an approved Oil and Gas Development Plan or any associated Drilling and Spacing Units, Form 2As, or Form 2s if the Director has reasonable cause to believe that information submitted on an application was materially incorrect. An Operator may petition the Commission to review the Director's decision. The Commission will hear the petition at its next regularly scheduled hearing.

2 CCR 404-1-310

37 CR 16, August 25, 2014, effective 9/30/2014
38 CR 01, January 10, 2015, effective 2/14/2015
38 CR 03, February 10, 2015, effective 3/2/2015
38 CR 07, April 10, 2015, effective 4/30/2015
38 CR 16, August 25, 2015, effective 9/14/2015
39 CR 04, February 25, 2016, effective 3/16/2016
41 CR 05, March 10, 2018, effective 4/1/2018
41 CR 06, March 25, 2018, effective 5/1/2018
41 CR 23, December 10, 2018, effective 12/30/2018
42 CR 02, January 25, 2019, effective 2/14/2019
42 CR 17, September 10, 2019, effective 9/30/2019
42 CR 24, December 25, 2019, effective 1/14/2020
43 CR 17, September 10, 2020, effective 9/30/2020
43 CR 13, July 10, 2020, effective 11/2/2020
43 CR 24, December 25, 2020, effective 1/15/2021
45 CR 07, April 10, 2022, effective 4/30/2022
45 CR 09, May 10, 2022, effective 5/30/2022
45 CR 13, July 10, 2022, effective 7/30/2022