2 Colo. Code Regs. § 404-1-1103

Current through Register Vol. 47, No. 20, October 25, 2024
Section 2 CCR 404-1-1103 - FLOWLINE AND CRUDE OIL TRANSFER LINE VALVES
1103.a.Isolation valve repair and maintenance.
(1) Operators must annually conduct one of the following maintenance operations on all isolation valves:
A. Perform a function test; or
B. Maintain the isolation valve in accordance with its manufacturer's specifications.
(2) Operators must repair or replace isolation valves that are not fully operable.
(3) On-location manifold, peripheral and process piping flowlines are exempt from the annual maintenance operations set forth in this section Rule 1103.a.(1).
1103.b. Any valve, flange, fitting or other component that is connected to a flowline or crude oil transfer line must have a manufacturer's specification rating that is equal to or greater than the maximum anticipated operating pressure.
1103.c. For all flowlines or crude oil transfer lines constructed after May 1, 2018, an isolation valve must be installed at each of the following locations before being placed into active status:
(1) On the suction end and the discharge end of a pump station in a manner that permits isolation of the pump station equipment in the event of an emergency;
(2) On each flowline or crude oil transfer line entering or leaving a breakout tank in a manner that permits isolation of the breakout tank from other facilities;
(3) At locations along a flowline or crude oil transfer line that will minimize damage or pollution from accidental discharge of hydrocarbons or E&P Waste, as appropriate for the terrain in open country or for populated areas;
(4) On each side of a flowline or crude oil transfer line crossing a Rule 317B Public Water System defined water supply or a waterbody that is more than 100 feet (30 meters) wide from high-water mark to high-water mark; and
(5) On each side of a flowline or crude oil transfer line crossing a reservoir storing water for human consumption.
1103.d. Flowlines and crude oil transfer lines constructed before May 1, 2018, must be retrofitted with isolation valves at each of the locations identified in Rule 1103.c.(1)-(5) by October 31, 2019. On-location manifold, peripheral and process piping flowlines are exempt from the retrofit provisions set forth in this section 1103.d.
1103.e. Check Valve Installation Requirements.
(1) Where an operator produces two or more wells through a common flowline, separator, or manifold, the operator must equip each flowline leading from a well to the common flowline, crude oil transfer line, separator, or manifold with a check valve or other comparable reverse flow prevention mechanism.
(2) The check valve or other comparable reverse flow prevention mechanism must be installed to permit fluids to move from the well to the common flowline, crude oil transfer line, separator, or manifold and to prevent any fluid from entering the well through the flowline.
(3) The operator must keep all check valves or other comparable reverse flow mechanisms in good working order.
(4) Upon the Director's request, operators must test the operation of the check valve or other comparable reverse flow mechanism.
(5) The requirements set forth in subsection (1) and (2) above, apply only to those check valves or comparable reverse flow mechanisms installed after May 1, 2018. Existing check valves or comparable reverse flow mechanisms must comply with subsection (3) and (4) above.

2 CCR 404-1-1103

37 CR 16, August 25, 2014, effective 9/30/2014
38 CR 01, January 10, 2015, effective 2/14/2015
38 CR 03, February 10, 2015, effective 3/2/2015
38 CR 07, April 10, 2015, effective 4/30/2015
38 CR 16, August 25, 2015, effective 9/14/2015
39 CR 04, February 25, 2016, effective 3/16/2016
41 CR 05, March 10, 2018, effective 4/1/2018
41 CR 06, March 25, 2018, effective 5/1/2018
41 CR 23, December 10, 2018, effective 12/30/2018
42 CR 02, January 25, 2019, effective 2/14/2019
42 CR 17, September 10, 2019, effective 9/30/2019
42 CR 24, December 25, 2019, effective 1/14/2020
43 CR 17, September 10, 2020, effective 9/30/2020
43 CR 13, July 10, 2020, effective 11/2/2020
43 CR 24, December 25, 2020, effective 1/15/2021
45 CR 07, April 10, 2022, effective 4/30/2022
45 CR 09, May 10, 2022, effective 5/30/2022
45 CR 13, July 10, 2022, effective 7/30/2022