Current through Register Vol. 47, No. 24, December 25, 2024
Section 7 CCR 1101-15-1-7 - ApplicabilityThe regulations contained herein shall apply to the operation of all LPG container assembly and piping systems including the following:
(a) Containers, piping and associated equipment, when delivering LPG to a building for use as a fuel gas.(b) Pipeline terminals, natural gasoline plants, refineries, tank farms, underground storage facilities, aboveground storage facilities and chemical plants utilizing LPG in the manufacture of their products.(c) The design, construction, installation and operation of pipeline terminals that receive LPG from pipelines under DOT jurisdiction, whose primary purpose is the receipt of LPG for delivery to transporters, distributors or users. Coverage shall begin downstream of the last pipeline valve or tank manifold inlet.40 CR 07, April 10, 2017, effective 5/1/201740 CR 17, September 10, 2017, effective 9/30/201747 CR 21, November 10, 2024, effective 11/30/2024