Tier | Description | Cost |
1 | Projects that incur minimal costs and water quality impacts | $1,122 |
2 | Projects that incur moderate costs and potential water quality impacts | $3,876 |
3 | Projects that involve large watershed area, a high degree of complexity, or a high potential for water quality impacts. | Calculated on an hourly rate based on the actual costs of Division staff and contractor time. |
4 | Projects that involve multiple or large watershed areas, a very high degree of complexity, very high potential for water quality impacts, or a high level of public involvement. | Calculated on an hourly rate based on the actual costs of Division staff and contractor time. |
5 CCR 1002-82.4