Section 5 CCR 1002-61.60 - STATEMENTOF BASIS, SPECIFIC STATUTORY AUTHORITY AND PURPOSE: NOVEMBER 13, 2007 RULEMAKING HEARING, EFFECTIVE DATE OF DECEMBER 30, 2007 - CONCENTRATED ANIMAL FEEDING OPERATIONS REGULATIONS

The provisions of sections 25-8-202(1)(d) and (2) and 25-8-501 to 25-8-504, C.R.S., provide the specific statutory authority for the amendments to this regulation adopted by the Water Quality Control Commission (Commission). The Commission has also adopted, in compliance with section 24-4-103(4) C.R.S., the following statement of basis and purpose.

BASIS AND PURPOSE

A.APPLICABILITY

The provisions in Commission Regulation No. 61, 5 CCR 1002-61 (Regulation 61) section 61.17 apply to permits for concentrated animal feeding operations (CAFOs).

B.PURPOSE OF AMENDING THE STATE PROGRAM

In response to a February 28, 2005 Second Circuit Court of Appeals decision in Waterkeeper Alliance et al., v. EPA, 399 F. 3d 486 (2nd Cir. 2005) (Waterkeeper), that vacated the requirement for CAFOs to apply for a National Pollutant Discharge Elimination System (NPDES) permit or otherwise demonstrate no potential to discharge, as well as remanding portions of the CAFO Rule back to EPA for further revision and clarification, the EPA finalized a rule change revising certain compliance dates to allow the agency sufficient time to revise the CAFO Rule to comply with this decision. The February 10, 2006 final rule:

1) extended the date by which operations defined as CAFOs as of April 14, 2003, who were not defined as CAFOs prior to that date, must seek permit coverage from February 13, 2006 to July 31, 2007;
2) extended the deadline for operations which became defined as CAFOs after April 14, 2003, and that are not new sources, to seek permit coverage from April 13, 2006 to July 31, 2007; and
3) extended the deadline by which permitted CAFOs are required to develop and implement NMPs from December 31, 2006 until July 31, 2007.

Because EPA is continuing to work on a final rule in response to the Waterkeeper decision, and did not complete the rulemaking prior to the July 31, 2007 deadline set by EPA's February 10, 2006 rule, EPA finalized a second rule change revising all of the above compliance dates from July 31, 2007 to February 27, 2009.

The Commission agrees with the staff recommendation that it is appropriate to revise the deadlines in section 61.17 of Regulation No. 61 to be consistent with the new EPA deadlines.

To this end, the Commission revised certain compliance deadlines according to EPA's July 24, 2007 rule that will be reflected in the Colorado Discharge Permit System general permit for CAFOs.

C.DISCUSSION OF AMENDED SECTIONS

Scope and Purpose The Commission modified section 61.17 to make clear that section 61.17 contains the revised compliance dates for NMPs and newly defined CAFOs as reflected in EPA's July 24, 2007 rule.

Permit Application Deadlines Sections 61.17 were revised to reflect the new permit application deadline of February 27, 2009, for newly defined CAFOs.

NMP Development and Implementation Deadline The Commission modified section 61.17 and 61.17 to reflect the new deadline of February 27, 2009, which is the revised date by which CAFOs are required to develop and implement NMPs. In addition, the Commission modified section 61.17 to reflect that the deadline for NMP development and implementation for existing source CAFOs is February 27, 2009 or upon the date of permit coverage, whichever is later.

5 CCR 1002-61.60

38 CR 01, January 10, 2015, effective 1/30/2015
38 CR 11, June 10, 2015, effective 6/30/2015
39 CR 17, September 10, 2016, effective 12/31/2016
39 CR 21, November 10, 2016, effective 12/31/2016
40 CR 07, April 10, 2017, effective 4/30/2017
41 CR 23, December 10, 2018, effective 12/30/2018
43 CR 10, May 25, 2020, effective 6/14/2020