5 Colo. Code Regs. § 1002-51.27

Current through Register Vol. 47, No. 11, June 10, 2024
Section 5 CCR 1002-51.27 - Statement of Basis, Specific Statutory Authority, and Purpose (1997 Revisions)

The provisions of sections 25-8-202(1)(e), and (g); 25-8-308(1)(d); and 37-95-107.6(4) C.R.S. provide the specific statutory authority for adoption of the attached regulatory amendments. The Commission also adopted, in compliance with section 24-4-103(4) C.R.S., the following statement of basis and purpose.

Basis and Purpose

The Federal Clean Water Act and the Environmental Protection Agency have authorized flexibility to state revolving fund programs by encouraging states to fund "expandable uses" and integrate other water quality eligibilities into their priority systems and plans for distributing funds. The Water Quality Control Commission authorized a critical review team to review and propose revisions to the existing Water Pollution Control Revolving Fund (WPCRF) Rules 5.2.0 (5 CCR 1002-21) to assist communities that are proactive with compliance issues and encourage pollution prevention. With these broad directions in place, the Interim WPCRF Rules with expanded eligibilities were proposed.

The existing WPCRF Rules have separate priority ranking systems for point source (wastewater projects defined by Section 212 of the Federal Act) and nonpoint source projects. The nonpoint source priority system has not been utilized since 1992. The point source priority system required points to be compiled for each project; first for severity of pollution problems, then for quality of receiving waters, financial need, regionalization, water conservation and beneficial use.

The Interim WPCRF Rules provide for a list of all projects that improve or benefit water quality with emphasis on public health, and proactive and long range planning of water quality approaches and/or pollution prevention methods. A more detailed prioritization will be assembled if there is a shortage of funds available.

This interim rule provides two major benefits:

Even though traditional wastewater projects are still a priority and will be identified as such, this rule will allow communities to receive low interest loans for other water quality concerns in their area, such as: stormwater, biosolids, water reuse, landfills, etc.

The effort of compiling the project list will be more strategic with planning and watershed efforts, more accurate with addressing actual water quality needs, less subjective and less resource intensive as far as collecting data to prioritize each project (which would be very difficult with such diverse types of projects).

In subsection (a) of section 5.2.9 , Procedures for Identifying Projects and Establishing the Project Eligibility List, the Commission has included broader language regarding consultation than appears in the existing rule. The purpose of this language is to further strengthen the WPCRF program by broadening community involvement. The Commission is hopeful that this will result in more timely and accurate needs assessment information, improved coordination between different funding sources, and ongoing feedback on the WPCRF program.

The critical review team recommended that the Commission adopt an interim rule to assess the outcome of such a radical change in prioritizing water quality projects in Colorado before permanently changing this regulation. Therefore, this rulemaking has not repealed the existing regulatory provisions, but rather provides that the new Interim Rules will apply for purposes of developing a FY98 Intended Use Plan. It is anticipated that this Interim WPCRF Rule will be reviewed in an informational hearing in November, 1997, to receive input on the operation of the Interim Rules and whether they should be modified, repealed, or made permanent.

5 CCR 1002-51.27

38 CR 17, September 10, 2015, effective 9/30/2015