The provisions of C.R S. 25-8-202(1)(a), (b) and (2); 25-8-203; 25-8-204; and 25-8-402; provide the specific statutory authority for adoption of these regulatory amendments. The Commission also adopted in compliance with 24-4-103(4) C.R.S. the following statement of basis and purpose.
BASIS AND PURPOSE
Pursuant to the requirements in the Basic Standards (at 31.7(3)), the Commission reviewed the status of temporary modifications to determine whether the temporary modification should be modified, eliminated or extended.
The type iii temporary modification of ammonia standards on La Plata segment 7a was reviewed. It will expire on 12/31/2012. It is anticipated that site-specific standards will be considered as part of the basin-wide review in June 2012.
Temporary modifications of metal standards in the Upper Animas Basin (Animas River segments 2, 3a, 3b, 3c, 4a, 4b, 7, 8 and 9) were reviewed. They will expire on 12/31/2012. It is anticipated that the Animas River Stakeholder Group will present a more comprehensive review as part of the basin-wide review in June 2012.
The temporary modifications of the iron standard on San Juan segment 11a and La Plata segment 8a were reviewed. They will expire on 12/31/2012. When originally adopted, time was allotted to allow dischargers time to assess potential changes to their discharge permits. It is anticipated that these will be addressed as part of the basin-wide review in June 2012.
PARTIES TO THE RULEMAKING HEARING
5 CCR 1002-34.36