5 Colo. Code Regs. § 1001-5-D-III

Current through Register Vol. 48, No. 1, January 10, 2025
Section 5 CCR 1001-5-D-III - Permit Review Procedures
III.A. Major stationary sources subject to the requirements of this Part D must apply for and obtain a Construction Permit in accordance with the procedures and requirements in Part B or an Operating permit in accordance with the procedures and requirements in Part C.
III.B. The Division shall complete the processing of applications (including any requested public hearing) for sources subject Sections VI. and VII. of this Part D within twelve months of receipt of a complete application.

5 CCR 1001-5-D-III

37 CR 18, September 25, 2014, effective 10/15/2014
37 CR 24, December 25, 2014, effective 1/14/2015
39 CR 04, February 25, 2016, effective 3/16/2016
39 CR 21, November 10, 2016, effective 11/30/2016
41 CR 21, November 10, 2018, effective 11/30/2018
43 CR 02, January 25, 2020, effective 2/14/2020
44 CR 02, January 25, 2021, effective 2/14/2021
46 CR 02, January 25, 2022, effective 2/14/2023
46 CR 12, June 25, 2023, effective 7/15/2023
47 CR 06, March 25, 2024, effective 4/15/2024
47 CR 12, June 25, 2024, effective 7/15/2024