Current through Register Vol. 48, No. 1, January 10, 2025
Section 5 CCR 1001-5-A-III - Administrative Permit Amendment ProceduresIII.A. An application for an administrative permit amendment shall be prepared on forms supplied by the Division.III.B. Within sixty calendar days after receipt of a complete application for an administrative permit amendment the Division shall issue its final determination on such application in accordance with the following: III.B.1. Deny the application for an administrative permit amendment; orIII.B.2. Grant the application and incorporate any such changes into the permit providing such permit revisions are made pursuant to this Part A, Section III.III.C. A source may implement the changes addressed in the application for an administrative amendment immediately upon submittal of request, subject to the final determination of the Division.III.D. As required under the Federal Act, the Division shall transmit to the Administrator a copy of each revised permit made pursuant to an administrative permit amendment under this provision.III.E. No public notice or review by affected states shall be necessary for permit revisions made pursuant to administrative amendment procedures.III.F. Administrative permit amendments for purposes of the acid rain portion of a permit shall be governed by regulations promulgated under Title IV of the Federal Act, found at Code of Federal Regulations Title 40, Part 72.37 CR 18, September 25, 2014, effective 10/15/201437 CR 24, December 25, 2014, effective 1/14/201539 CR 04, February 25, 2016, effective 3/16/201639 CR 21, November 10, 2016, effective 11/30/201641 CR 21, November 10, 2018, effective 11/30/201843 CR 02, January 25, 2020, effective 2/14/202044 CR 02, January 25, 2021, effective 2/14/202146 CR 02, January 25, 2022, effective 2/14/202346 CR 12, June 25, 2023, effective 7/15/202347 CR 06, March 25, 2024, effective 4/15/202447 CR 12, June 25, 2024, effective 7/15/2024