Section 5 CCR 1001-10-D-X - Enforcement
X.A. All base year or post-reduction emissions information described in Section V. and required to be submitted as part of a permit application under Section VII. shall be considered to have been requested by the Administrator under the authority of Section 114 of the Federal act or by the Division under Section 25-7-111(2)(i) of the Act.
X.B. Fraudulent-statements contained in any base year or post-reduction emissions submitted to the Division or EPA Regional Office under this Regulation shall be considered violations of Section 114 of the Federal act and of this regulation and, thus, actionable under Section 113 of the Federal act and can be considered, in appropriate cases, violations of 18 U.S.C. § 1001, the general false swearing provision of the United States Code, and/or under Section 25-7-122.1(2) of the Act
X.C. If an early reduction in a permit application filed under Section VII is disapproved, the owner or operator shall comply with an applicable standard issued under Section 112(d) of the Federal act and/or Section 25-7-109.3(3) of the Act by the compliance date specified in each standard.
X.D. A violation of an alternative emission limitation or other requirement established by permit under Section IX.A. or B. for the source is enforceable pursuant to the authority of Section 113 of the Federal act and enforcement provisions of the Act notwithstanding any demonstration of continuing 90 percent (95 percent for hazardous air pollutants which are particulates) emission reduction over the entire source.

5 CCR 1001-10-D-X

37 CR 18, September 25, 2014, effective 10/15/2014
38 CR 05, March 10, 2015, effective 3/30/2015
38 CR 18, September 25, 2015, effective 10/15/2015
39 CR 18, September 25, 2016, effective 10/15/2016
40 CR 12, June 25, 2017, effective 7/15/2017
41 CR 11, June 10, 2018, effective 6/30/2018
42 CR 16, August 25, 2019, effective 9/14/2019
43 CR 03, February 10, 2020, effective 1/16/2020
43 CR 03, February 10, 2020, effective 3/1/2020
43 CR 12, June 25, 2020, effective 7/15/2020
44 CR 04, February 25, 2021, effective 3/17/2021
44 CR 12, June 25, 2021, effective 7/15/2021
45 CR 12, June 25, 2022, effective 7/15/2022
46 CR 12, June 25, 2023, effective 7/15/2023
47 CR 12, June 25, 2024, effective 7/15/2024