5 Colo. Code Regs. § 1001-10-D-VII

Current through Register Vol. 47, No. 20, October 25, 2024
Section 5 CCR 1001-10-D-VII - Application Procedures
VII.A. To apply for an alternative emission limitation under Section III., an owner or operator of the source shall file an appropriate permit application with the permitting authority.
VII.B. The permit application shall contain a demonstration of early reduction for the source as prescribed in Section V. and the additional information required for a complete permit application as specified by the Division's permitting program approved under Title V of the Federal act and/or under Section 25-7-114.3 of the Act
VII.C. Permit applications under this section shall be submitted by the later of the following dates:
VII.C.1. The date of proposal of an otherwise applicable standard issued under Section 112(d) of the Federal act or, Section 25-7-109.3(3) of the Act.
VII.C.2. 120 days after approval of the Division's permit program under Title V of the Federal act
VII.D. If a source test is the supporting basis for establishing post-reduction emissions for one or more emission points in the source but the test results are not available by the deadline for submittal of a permit application according to Section VIII.C., the owner or operator shall provide the supporting basis no later than 120 days after the applicable deadline for submittal of the permit application.
VII.E. Review and disposition of permit applications submitted under this section will be accomplished according to 40 CFR Part 70 and/or Section 25-7-114.3 of the Act

5 CCR 1001-10-D-VII

37 CR 18, September 25, 2014, effective 10/15/2014
38 CR 05, March 10, 2015, effective 3/30/2015
38 CR 18, September 25, 2015, effective 10/15/2015
39 CR 18, September 25, 2016, effective 10/15/2016
40 CR 12, June 25, 2017, effective 7/15/2017
41 CR 11, June 10, 2018, effective 6/30/2018
42 CR 16, August 25, 2019, effective 9/14/2019
43 CR 03, February 10, 2020, effective 1/16/2020
43 CR 03, February 10, 2020, effective 3/1/2020
43 CR 12, June 25, 2020, effective 7/15/2020
44 CR 04, February 25, 2021, effective 3/17/2021
44 CR 12, June 25, 2021, effective 7/15/2021
45 CR 12, June 25, 2022, effective 7/15/2022
46 CR 12, June 25, 2023, effective 7/15/2023
47 CR 12, June 25, 2024, effective 7/15/2024