Section 6 CCR 1007-1-5.13 - Permanent Radiographic Installations
5.13.1 Each entrance that is used for personnel access to the high radiation area in a permanent radiographic installation must have either.
5.13.1.1 An entrance control of the type described in Part 4, Section 4.19 of these regulations that causes the radiation level upon entry into the area to be reduced; or
5.13.1.2 Both conspicuous visible and audible warning signals to warn of the presence of radiation. The visible signal must be actuated by radiation whenever the source is exposed or the machine is energized. The audible signal must be actuated when an attempt is made to enter the installation while the source is exposed or the machine is energized.
5.13.2 The alarm system must be tested for proper operation with a radiation source each day before the installation is used for radiographic operations. The test must include a check of both the visible and audible signals. Entrance control devices that reduce the radiation level upon entry as designated in 5.13.1 must be tested monthly.
5.13.3 If an entrance control device or an alarm is operating improperly, it must be immediately labeled as defective and repaired within 7 calendar days. The facility may continue to be used during this 7-day period, provided the licensee or registrant implements the continuous surveillance requirements of 5.22 and uses an alarming ratemeter. Test records for entrance controls and audible and visual alarms must be maintained in accordance with 5.31.

6 CCR 1007-1-5.13

Colorado Register, Vol 37, No. 14. July 25, 2014, effective 8/14/2014
38 CR 02, January 25, 2015, effective 2/14/2015
38 CR 05, March 10, 2015, effective 3/30/2015
38 CR 12, June 25, 2015, effective 7/15/2015
38 CR 14, July 25, 2015, effective 8/14/2015
39 CR 02, January 25, 2016, effective 2/14/2016
39 CR 16, August 25, 2016, effective 9/14/2016
39 CR 22, November 25, 2016, effective 12/15/2016
40 CR 11, June 10, 2017, effective 6/30/2017
40 CR 20, October 25, 2017, effective 11/14/2017
42 CR 24, December 25, 2019, effective 1/14/2020
43 CR 14, July 25, 2020, effective 8/14/2020
43 CR 18, September 25, 2020, effective 10/15/2020
44 CR 11, June 10, 2021, effective 7/15/2021
44 CR 14, July 25, 2021, effective 8/14/2021
45 CR 22, November 25, 2022, effective 12/15/2022