The applicant shall provide a statement of need which will consist of:
- 2,000 BTU/ft2 hr zone;
- 1,000 BTU/ft2hr zone;
- 460 BTU/ft2 hr zone; and the
- vapor dispersion zone.
FIGURE 1
CAPITAL COST MATRIX | ||
FACTORS | SITE A | SITEB |
Land Acquisition | $ | $ |
Site Preparation Structures and Improvements LNG Processing Equipment LNG Transportation Facilities Other Equipment | ||
TOTAL | $ | $ |
FIGURE 2
ANNUAL COST MATRIX | ||
FACTORS | SITE A | SITEB |
Operating Expenses Maintenance Expenses | $ | $ |
TOTAL | $ | $ |
FIGURE 3
ENVIRONMENTAL MATRIX
SITE A | SITEB | |
FACTORS | COMPARATIVE RATING | COMPARATIVE RATING |
Ease of Acquisition | ||
Climatology | ||
Geology | ||
Hydrology | ||
Transportation Access | ||
Ecological Sensitivity | ||
Socioeconomics | ||
Special Resources | ||
Commitment | ||
Other |
- The ratings should be based upon the total number of sites proposed (number of sites = n). The most preferred site for each factor should receive a rating of n. The site preferred next should be rated n-1, and so forth.
- Reconnaissance level data may be employed in constructing the environmental matrix, including existing studies and reports completed by public or private agencies. If such sources are not available or adequate, site analyses must be conducted.
- The environmental matrix shall be accompanied by a narrative which references the sources of the data used for each factor and an explanation of how these data were used to arrive at the relative rating for each proposed site.
980 CMR, § 10.02