In addition to LID controls outlined in this section (974 CMR 4.08) or the Handbook, flood management and culvert replacement projects shall assess, and to the maximum extent feasible implement, stream daylighting1 and improved channel connectivity2.
1 "Stream daylighting" means the practice of exposing some or all of a previously buried river, stream, and/or stormwater drainage and restoring the watercourse to a more natural condition.
2 "Channel connectivity" means the degree to which hydrologic components of a river system or watershed are joined, or connected, by various transport mechanisms including streams, non-tidal wetlands, riparian buffers, or underground aquifers.
3 Pollutant removal is calculated based on average annual loading and not on the basis of any individual storm event.
* Alternative comparable reinforcement methods will be considered by the DEC on a case-by-case basis.
974 CMR, § 4.08