The Eligible Applicant shall, in collaboration with the Owner's Project Manager, maintain all original closeout documentation and shall provide such documentation to the Authority as a complete submittal with the hard copy of the final reimbursement request.
All closeout submissions must be received and activities completed to the satisfaction of the Authority, and in accordance with the timelines established by the Authority. The Authority may require additional materials and information related to the reconciliation of project costs.
The MSBA shall prepare the Final Audit Report as set forth in 963 CMR 2.17(3) and provide it to the Eligible Applicant. The procedures for the review and acceptance of the final audit report by the Eligible Applicant are established in 963 CMR 2.17(3).
963 CMR, § 2.13