950 CMR, § 62.12

Current through Register 1533, October 25, 2024
Section 62.12 - Computation of Time

Computation of any period of time referred to in 950 CMR 62.00 shall begin with the first day following the act which initiates such period of time when the last day of the period so computed is a day on which the office is closed, the period shall run until the end of business on the date the Division is next open for business when such period of time, with intervening Saturdays, Sundays and legal holidays counted is five days or less than said Saturdays, Sundays and legal holidays shall be excluded from the computation.

950 CMR, § 62.12